Buildings and Facilities19O00058

RETROFITTING OF GOVERNMENMT BUILDINGS IN PREPARATION FOR THE BIG ONE-QUIRINO HIGH SCHOOL, RIZAL BUILDING, MOLAVE STREET, PROJECT 3, QUEZON CITY

RETROFITTING OF GOVERNMENMT BUILDINGS IN PREPARATION FOR THE BIG ONE-QUIRINO HIGH SCHOOL, RIZAL BUILDING, MOLAVE STREET, PROJECT 3, QUEZON CITY is a DPWH-tracked public work in National Capital Region, National Capital Region. Reported contract value: ₱17,369,616.81. Status: Reported complete (DPWH). Contractor on record: RAICON DEVELOPMENT CORP FORMERLY : RA IGNACIO CONST CORP. Figures trace to dpwh.

National Capital Region, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱17,369,616.81

Progress

Reported complete (DPWH)

Start Date

January 20, 2020

Target End

April 16, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.