Roads22DD0091

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION REHABILITATION OF ROAD AT BARANGAY ANILAO LABAC, LIPA

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION REHABILITATION OF ROAD AT BARANGAY ANILAO LABAC, LIPA is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱6,722,357.00. Status: Reported complete (DPWH). Contractor on record: MEGAJES CONST CORP. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Flood Mitigation Structures protecting Public Infrastructures/ Facilities at Barangay Quezon, Lipa City, Batangas
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Batangas 4th DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

36 projects · ₱426.6M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE, M

Batangas 4th DEO, Region IV-A

2024₱29.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHABILITATION OF QUILO-QUILO-SAN CARLOS

Batangas 4th DEO, Region IV-A

2024₱28.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAWI AND BANABA CREEK, PAD

Batangas 4th DEO, Region IV-A

2024₱28.5M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (CHED), LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2021₱19.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT BARANGAY SABANG, LIPA CITY BATANGAS

Batangas 4th DEO, Region IV-A

2024₱19.2M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING IN BAGONG POOK ELEMENTARY SCHOOL, BRGY. BAGONG POOK, ROSARIO, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱16.9M
Past target date (DPWH On-Going)
View all 36 projects →

4. Implementation

Contract Amount

₱6,722,357.00

Progress

Reported complete (DPWH)

Start Date

April 4, 2022

Target End

June 4, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.