Bridges24DL0057

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES 1. BAYOD BR. (B03109LZ) ALONG TALABA-SUMMIT-PANAON RD

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES 1. BAYOD BR. (B03109LZ) ALONG TALABA-SUMMIT-PANAON RD is a DPWH-tracked public work in Quezon 4th DEO, Region IV-A. Reported contract value: ₱5,243,000.00. Status: Reported complete (DPWH). Contractor on record: JEMAK CONST. Figures trace to dpwh.

Quezon 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage Structure along Calauag River, Calauag, Quezon
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Quezon 4th DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱5,243,000.00

Progress

Reported complete (DPWH)

Start Date

February 7, 2024

Target End

August 8, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.