Flood Control and Drainage23CD0209

REHABILITATION OF FLOOD CONTROL STRUCTURE AT PANDAYAN CREEK (MANZANO SECTION), BARANGAY PANDAYAN, MARILAO, BULACAN

REHABILITATION OF FLOOD CONTROL STRUCTURE AT PANDAYAN CREEK (MANZANO SECTION), BARANGAY PANDAYAN, MARILAO, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱44,389,073.49. Status: Reported complete (DPWH). Contractor on record: TRIPLE 8 CONST. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Barangay Lalakhan, Santa Maria, Bulacan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bulacan 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

276 projects · ₱13.4B total · 0 flags

Other projects by this contractor

CONSTRUCTION OF REVETMENT ALONG MARIBLO CREEK, STA. 0+010.000 TO STA. 0+524.458 (LEFT AND RIGHT RIVER BANK), QUEZON CITY

Flood Control Management Cluster, Central Office

2021₱195.0M
Reported complete (DPWH)
No sat.

REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADSBACOOR - DASMARIÑAS NATIONAL RD. - K0028 + 215 - K0028 + 404, K0029 + 204 - K0029 + 780, K0029 + 822 - K0030 + 675, K0030 + 716 - K0030 + 1002, K0031 + 015 - K0031 + 609

Region IV-A, Region IV-A

2023₱154.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

REHABILITATION OF CAMP AGUINALDO ROAD NETWORK, PACKAGE A, QUEZON CITY

Quezon City 2nd DEO, National Capital Region

2025₱141.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF REVETMENT ALONG DARIO CREEK, STA. 0+020.000 TO STA. 0+351.894 (LEFT AND RIGHT RIVER BANK), QUEZON CITY

Flood Control Management Cluster, Central Office

2021₱135.7M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM-NATIONAL BUILDING PROGRAM-BUILDINGS AND OTHER STRUCTURES-MULTI-PURPOSE/FACILITIES-CONSTRUCTION OF OPEN UNIVERSITY SYSTEM BUILDING IN POLYTECHNIC UNIVERSITY OF THE PHILIPPINES (PUP) PHASE II AT PUP A. MABINI CAMPUS, STA. MESA, MANILA

South Manila DEO, National Capital Region

2023₱111.0M
Reported complete (DPWH)

LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM, FLOOD CONTROL AND DRAINAGE, FLOOD CONTROL STRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT ALONG IMUS RIVER, BRGY. BUHAY NA TUBIG, PHASE IV, IMUS CITY, CAVITE

Cavite 1st DEO, Region IV-A

2019₱99.0M
Reported complete (DPWH)
View all 276 projects →

4. Implementation

Contract Amount

₱44,389,073.49

Progress

Reported complete (DPWH)

Start Date

February 26, 2024

Target End

October 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.