Buildings and Facilities25KG0035

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY PUNTOD, MATUNGAO, LANAO DEL NORTE

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY PUNTOD, MATUNGAO, LANAO DEL NORTE is a DPWH-tracked public work in Lanao del Norte 1st DEO, Region X. Reported contract value: ₱5,850,025.36. Status: Past target date (DPWH On-Going). Contractor on record: ALQAOD CONST AND SUPPLY 39078. Figures trace to dpwh.

Lanao del Norte 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Sagadan Bridge (B00961MN), Package 1, Tubod, Lanao del Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Lanao del Norte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 39078

41 projects · ₱239.2M total · 0 flags

4. Implementation

Contract Amount

₱5,850,025.36

Progress

Past target date (DPWH On-Going)

Start Date

June 4, 2025

Target End

November 21, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.