Roads23MG0019

CONSTRUCTION OF CONCRETE ROAD-ROAD FROM JUNCTION LAKE SEBU TO VILLA ELLAGA-LAMBUSONG ROAD LINKING PROVINCIAL ROAD IN SUPPORT OF PINEAPPLE, PALM OIL,CORN,BANANA,CASSAVA AND SUGARCANE AT BARANGAY COLONGULO TO PACKAGING AND PROCESSING CENTERS, SURALLAH, SOUT

CONSTRUCTION OF CONCRETE ROAD-ROAD FROM JUNCTION LAKE SEBU TO VILLA ELLAGA-LAMBUSONG ROAD LINKING PROVINCIAL ROAD IN SUPPORT OF PINEAPPLE, PALM OIL,CORN,BANANA,CASSAVA AND SUGARCANE AT BARANGAY COLONGULO TO PACKAGING AND PROCESSING CENTERS, SURALLAH, SOUT is a DPWH-tracked public work in South Cotabato 2nd DEO, Region XII. Reported contract value: ₱33,319,912.83. Status: Reported complete (DPWH). Contractor on record: PASE CONST 15849. Figures trace to dpwh.

South Cotabato 2nd DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Kolambog Flood Control/Slope Protection (Sheet Piles) along Cotabato-Marbel Road (Allah River, Kolambog Section), South Cotabato
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

South Cotabato 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱33,319,912.83

Progress

Reported complete (DPWH)

Start Date

February 17, 2023

Target End

September 14, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.