Bridges24PA0044

REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, SOOT BRIDGE (B00989LZ) ALONG ABRA-ILOCOS NORTE ROAD, LA PAZ, ABRA

REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, SOOT BRIDGE (B00989LZ) ALONG ABRA-ILOCOS NORTE ROAD, LA PAZ, ABRA is a DPWH-tracked public work in Abra DEO, Cordillera Administrative Region. Reported contract value: ₱4,583,018.73. Status: Past target date (DPWH On-Going). Contractor on record: TUQUER BUILDERS 36753. Figures trace to dpwh.

Abra DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Malabbaga Flood Control Structure, Malabbaga, La Paz, Abra
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Abra DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,583,018.73

Progress

Past target date (DPWH On-Going)

Start Date

July 17, 2024

Target End

September 30, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.