Roads18DG0074

CONCRETING OF BRGY. DALUSAG (PROPER)FMR, BRGY. DALUSAG (PROPER), GEN. EMILIO AGUINALDO, 18DG0074

CONCRETING OF BRGY. DALUSAG (PROPER)FMR, BRGY. DALUSAG (PROPER), GEN. EMILIO AGUINALDO, 18DG0074 is a DPWH-tracked public work in Cavite 2nd DEO, Region IV-A. Reported contract value: ₱5,659,044.29. Status: Reported complete (DPWH). Contractor on record: CBS CONST AND CONST SUPPLY. Figures trace to dpwh.

Cavite 2nd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment along Cañas River, Brgy. Pinagtipunan Section,Phase 2, Gen. Trias, Cavite
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-18-0004216

₱65,506.00 · FY2018

Released to Cavite District Engineering Office Trust Receipt (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱5,659,044.29

Progress

Reported complete (DPWH)

Start Date

June 4, 2018

Target End

August 2, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.