GAA 2025 SSP25BD0031

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONCRETING OF BRGY. LANNA - SITIO NARUANG -BATU, ENRILE, CAGAYAN - PHASE II

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONCRETING OF BRGY. LANNA - SITIO NARUANG -BATU, ENRILE, CAGAYAN - PHASE II is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱4,753,379.14. Status: Past target date (DPWH On-Going). Contractor on record: KNI88 HARDWARE AND CONST SUPPLY. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures Along Paranan River, Baggao, Cagayan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cagayan 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

25 projects · ₱117.1M total · 0 flags

Other projects by this contractor

No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONCRETING OF BRGY. LANNA - SITIO NARUANG - BATU, ENRILE, CAGAYAN

Cagayan 3rd DEO, Region II

2024₱17.6M
Past target date (DPWH On-Going)
No sat.

CONST./IMP. OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES- JUNCTION SANTIAGO-TUGUEGARAO ROAD-MAGALALAG-ABA-SAN MIGUEL-ROMA LEADING TO CAGAYAN RUBINA SUGAR MILLING COMPANY (CARSUMCO) AND AGRI-BUSINESS INDUSTRY, ENRILE, CAGAYAN- PACKAGE 2

Cagayan 3rd DEO, Region II

2024₱13.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROADS AND DRAINAGES AT MUNICIPALITY OF ENRILE, CAGAYAN

Cagayan 3rd DEO, Region II

2025₱6.7M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI- PURPOSE BUILDING, BRGY. LEMU SUR, ENRILE, CAGAYAN

Cagayan 3rd DEO, Region II

2024₱4.9M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI- PURPOSE BUILDING, BRGY. SAN ANTONIO, ENRILE, CAGAYAN

Cagayan 3rd DEO, Region II

2024₱4.9M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI- PURPOSE BUILDING, BARANGAY LEMU NORTE, ENRILE, CAGAYAN

Cagayan 3rd DEO, Region II

2024₱4.9M
Reported complete (DPWH)
View all 25 projects →

4. Implementation

Contract Amount

₱4,753,379.14

Progress

Past target date (DPWH On-Going)

Start Date

August 14, 2025

Target End

November 26, 2025

5. Audit