Buildings and Facilities16BF0038

CONSTRUCTION OF 2STY 4CL SCHOOL BUILDING AT MALALINTA NATIONAL HIGH SCHOOL, SAN MANUEL, ISABELA

CONSTRUCTION OF 2STY 4CL SCHOOL BUILDING AT MALALINTA NATIONAL HIGH SCHOOL, SAN MANUEL, ISABELA is a DPWH-tracked public work in Isabela 2nd DEO, Region II. Reported contract value: ₱5,973,177.14. Status: Reported complete (DPWH). Contractor on record: JMU CONST 6877. Figures trace to dpwh.

Isabela 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱5,973,177.14

Progress

Reported complete (DPWH)

Start Date

August 23, 2016

Target End

April 29, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.