Buildings and Facilities16DJ0015

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, SAN ANTONIO, QUEZON 2ND LD

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, SAN ANTONIO, QUEZON 2ND LD is a DPWH-tracked public work in Quezon 2nd DEO, Region IV-A. Reported contract value: ₱4,950,000.00. Status: Reported complete (DPWH). Contractor on record: BOMEL CONST. Figures trace to dpwh.

Quezon 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

77 projects · ₱1.4B total · 0 flags

Other projects by this contractor

No sat.

(SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF GUINAYANGAN - TAGKAWAYAN ROAD (SAN ROQUE - SEGUIWAN - KATIMO - KINATAKUTAN SECTION), TAGKAWAYAN, QUEZON

Quezon 4th DEO, Region IV-A

2024₱112.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, 17. CONSTRUCTION/ IMPROVEMENT OF ACCESS R

Quezon 4th DEO, Region IV-A

2023₱106.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM, BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 15. REHABILITATION OF SUMULONG-GUINAYANGAN ROAD, GUINAYANGAN, QUEZON

Quezon 4th DEO, Region IV-A

2023₱99.0M
Reported complete (DPWH)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PIRIS RIVER, BUENAVISTA, PACKAGE 1, QUEZON, BUENAVISTA, QUEZON

Quezon 3rd DEO, Region IV-A

2024₱96.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS 6. GUINAYANGAN-TAGKAWAYAN DIVERSION ROAD, QUEZON

Quezon 4th DEO, Region IV-A

2022₱66.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING - PRIMARY ROADS 2. QUIRINO H-WAY - K0264 + 406 - K0265 + 140

Quezon 4th DEO, Region IV-A

2024₱47.5M
Reported complete (DPWH)
View all 77 projects →

4. Implementation

Contract Amount

₱4,950,000.00

Progress

Reported complete (DPWH)

Start Date

March 21, 2016

Target End

September 16, 2016

5. Audit