Flood Control and Drainage18DH0016

CONSTRUCTION/MAINTENANCE FOR FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM, CONSTRUCTION OF RIVER CONTROL ALONG PAGSANJAN RIVER, BRGY. SEGUNDA PULO, LUMBAN, LAGUNA

CONSTRUCTION/MAINTENANCE FOR FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM, CONSTRUCTION OF RIVER CONTROL ALONG PAGSANJAN RIVER, BRGY. SEGUNDA PULO, LUMBAN, LAGUNA is a DPWH-tracked public work in Laguna 1st DEO, Region IV-A. Reported contract value: ₱46,327,033.08. Status: Reported complete (DPWH). Contractor on record: NEWBIG FOUR J CONST INC FORMERLY: FOUR J CONST. Figures trace to dpwh.

Laguna 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱46,327,033.08

Progress

Reported complete (DPWH)

Start Date

February 8, 2018

Target End

October 18, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.