Buildings and Facilities16HL0107

PROVISION OF 1-UNIT TECH VOC WORKSHOP. . .@ TAMLANG HS, STA. CATALINA (NORTH DISTRICT), NEGROS ORIE

PROVISION OF 1-UNIT TECH VOC WORKSHOP. . .@ TAMLANG HS, STA. CATALINA (NORTH DISTRICT), NEGROS ORIE is a DPWH-tracked public work in Negros Oriental 3rd DEO, Negros Island Region. Reported contract value: ₱2,474,750.00. Status: Reported complete (DPWH). Contractor on record: BARILLO CONST AND ENT 23836. Figures trace to dpwh.

Negros Oriental 3rd DEO, Negros Island Region
Region: Negros Island Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 23836

137 projects · ₱2.3B total · 0 flags

Other projects by this contractor

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION/IMPROVEMENT OF FLOOD CONTROL FOR PREVENTION AND MITIGATION ALONG BRGY. SAN JOSE-POBLACION IMELDA, PART OF SIBUGUEY RIVER, IMELDA, Z

Region IX, Region IX

2019₱112.1M
Reported complete (DPWH)

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL ALONG KABASALAN RIVER (PHASE III), FL PENA, KABASALAN, ZAMBOANGA SIBUGAY

Region IX, Region IX

2021₱105.1M
Reported complete (DPWH)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE IV), FL PENA, KABASALAN, ZAMBOANGA SIBUGAY

Region IX, Region IX

2022₱104.9M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVERS BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE V), DOWNSTREAM, CANACAN, KABASALAN, ZAMBOANGA SIBUGAY, PACKAGE 1

Region IX, Region IX

2023₱104.8M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVERS BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE V), DOWNSTREAM, CANACAN, KABASALAN, ZAMBOANGA SIBUGAY, PACKAGE 2

Region IX, Region IX

2023₱100.0M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVERS BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE V), FL PENA, KABASALAN, ZAMBOANGA SIBUGAY, PACKAGE 1

Region IX, Region IX

2023₱100.0M
Reported complete (100% progress, DPWH status On-Going)
View all 137 projects →

4. Implementation

Contract Amount

₱2,474,750.00

Progress

Reported complete (DPWH)

Start Date

January 26, 2017

Target End

June 24, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.