Flood Control and Drainage18CG0057

REHABILITATION/IMPROVEMENT OF PAMPANGA RIVER ALONG STA. RITA (PHASE IV), SAN LUIS, PAMPANGA

REHABILITATION/IMPROVEMENT OF PAMPANGA RIVER ALONG STA. RITA (PHASE IV), SAN LUIS, PAMPANGA is a DPWH-tracked public work in Pampanga 1st DEO, Region III. Reported contract value: ₱91,578,513.50. Status: Reported complete (DPWH). Contractor on record: EDDMARI CONST. Figures trace to dpwh.

Pampanga 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱34,988,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Dawe River Sta. 0+000 - Sta. 3+150 at Minalin, Pampanga
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0014497

₱0.00 · FY2018

Released to Division of Pampanga (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

181 projects · ₱8.8B total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (STO. TOMAS-MINALIN SECTION), PACKAGE 5 AND PACKAGE 6, PROVINCE OF PAMPANGA

Region III, Region III

2023₱243.2M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (STO. TOMAS-MINALIN SECTION), PACKAGE 4, PROVINCE OF PAMPANGA

Region III, Region III

2021₱214.2M
Reported complete (DPWH)
No sat.

LOCAL INFRASTRUCTURE PROGRAM (LIP) -NATIONAL ROADS, CONSTRUCTION OF APALIT BYPASS ROAD CONNECTING TWO PROVINCES IN REGION III, BULACAN AND PAMPANGA

Region III, Region III

2017₱198.0M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (STO. TOMAS-MINALIN SECTION), PACKAGE 2, PROVINCE OF PAMPANGA

Region III, Region III

2020₱193.0M
Reported complete (DPWH)
No sat.

CONST./REP/REHAB./IMPR'VT. OF VARIOUS INFRA INCLUDING LOCAL PROJECTS-LOCAL ROADS & BRIDGES-LOCAL ROADS-REHAB./IMPR'VT. (UPGRADING & WIDENING TO 4-LANES WITH CONCRETE SLOPE PROTECTION) OF SAN MATIAS-STO. ROSARIO PAU ROAD, STO. TOMAS, PAMPANGA

Region III, Region III

2021₱193.0M
Reported complete (DPWH)

REHABILITATION/RESTORATION OF DETERIORATED DIKES/ERODED RIVERBANKS ALONG PAMPANGA RIVER INCLUDING CANDABA CUT-OFF CHANNEL, CANDABA, PAMPANGA (INLCUDING ROW), CANDABA AND SAN SIMON, PAMPANGA

Flood Control Management Cluster, Central Office

2018₱174.3M
Reported complete (DPWH)
View all 181 projects →

4. Implementation

Contract Amount

₱91,578,513.50

Progress

Reported complete (DPWH)

Start Date

April 18, 2018

Target End

September 14, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.