Roads24BG0012

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - SINAMAR NORTE VILLA FUERTE AND SAN M

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - SINAMAR NORTE VILLA FUERTE AND SAN M is a DPWH-tracked public work in Isabela 3rd DEO, Region II. Reported contract value: ₱4,877,598.24. Status: Reported complete (DPWH). Contractor on record: D A CADELIÑA CONST. Figures trace to dpwh.

Isabela 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Disabungan to Catalangan River Flood Control Project, Barangay Disusuan, San Mariano, Isabela
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Isabela 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

126 projects · ₱1.4B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF NEMMATAN FLOOD CONTROL STRUCTURE, SECTION 1, SAN AGUS

Isabela 4th DEO, Region II

2025₱106.1M
Past target date (DPWH On-Going)

LOCAL PROGRAM - CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - FLOOD CONTROL STRUCTURE/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CAGAYAN RIVER BANK - BRGY. PAPPAT, ANGADANAN, ISA

Isabela 3rd DEO, Region II

2021₱96.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - SANTIAGO-TUGUEGARAO ROAD - K0345+000 - K0346+825, SAN MATEO, ISABELA

Isabela 3rd DEO, Region II

2019₱48.5M
Reported complete (DPWH)
No sat.

OO1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - SANTIAGO-TUGUEGARAO RD - K0362+614 - K0363+725, CABATUAN, ISABELA

Isabela 3rd DEO, Region II

2022₱44.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - SANTIAGO CIRCUMFERENTIAL ROAD, ISABELA

Isabela 4th DEO, Region II

2023₱39.4M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - SANTIAGO - TUGUEGARAO RD - K0348 + 943 - K0350 + 000 , SAN MATEO, ISABELA

Isabela 3rd DEO, Region II

2021₱35.0M
Reported complete (DPWH)
View all 126 projects →

4. Implementation

Contract Amount

₱4,877,598.24

Progress

Reported complete (DPWH)

Start Date

April 8, 2024

Target End

May 25, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.