Flood Control and Drainage25DC0043

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES, CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG AGONCILLO SECTION, PHASE 4, TA

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES, CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG AGONCILLO SECTION, PHASE 4, TA is a DPWH-tracked public work in Batangas 3rd DEO, Region IV-A. Reported contract value: ₱53,074,819.50. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: V R PATRON BUILDERS. Figures trace to dpwh.

Batangas 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Mitigation Structure along Pansipit River, Lemery, Batangas (Phase 3)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Batangas 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

312 projects · ₱14.3B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF MISSING LINKS / NEW ROADSGENERAL AGUINALDO - MAGALLANES - NASUGBU ROAD (EAST - WEST ROAD), NASUGBU SECTION, PACKAGE 3, BATANGAS

Region IV-A, Region IV-A

2025₱327.6M
Ongoing (DPWH-reported)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-NAGA-JCT. MAGARAO-CANAMAN-LIBMANAN JCT. PPH ROAD (SKYBRIDGE), CAMARINES SUR PACKAGE 2, MAGARAO, CAMARINES SUR (

Region V, Region V

2024₱273.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT POBLACION BARANGAY I, SAN JOSE, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱244.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF MISSING LINKS / NEW ROADSGENERAL AGUINALDO - MAGALLANES - NASUGBU ROAD (EAST - WEST ROAD), INDANG - EAST SECTION, PACKAGE 4, CAVITE

Region IV-A, Region IV-A

2023₱209.4M
Past target date (DPWH On-Going)
No sat.

FY 2018 DPWH INFRASTRUCTURE PROGRAM ORGANIZATIONAL OUTCOME 1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF MISSING LINKS/NEW ROADS GEN. AGUINALDO-MAGALLANES-NASUGBU ROAD (EAST-WEST RD. AMADEO SECT., CAVITE

Region IV-A, Region IV-A

2018₱193.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARE

Batangas 3rd DEO, Region IV-A

2018₱193.0M
Reported complete (DPWH)
View all 312 projects →

4. Implementation

Contract Amount

₱53,074,819.50

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 21, 2025

Target End

October 16, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.