Buildings and Facilities19FN0070

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. CABUGAO, RAGAY, CAMARINES SUR

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. CABUGAO, RAGAY, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 1st DEO, Region V. Reported contract value: ₱4,801,432.77. Status: Reported complete (DPWH). Contractor on record: CASTLESTONE CONST AND SUPPLY. Figures trace to dpwh.

Camarines Sur 1st DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-19-0018815

₱0.00 · FY2019

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱4,801,432.77

Progress

Reported complete (DPWH)

Start Date

September 13, 2019

Target End

January 25, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.