Buildings and Facilities25GG0172

CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY MAGBATO, LAMBUNAO, ILOILO

CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY MAGBATO, LAMBUNAO, ILOILO is a DPWH-tracked public work in Iloilo 6th DEO, Region VI. Reported contract value: ₱3,440,140.76. Status: Past target date (DPWH On-Going). Contractor on record: H&S GUBANTES CONST. Figures trace to dpwh.

Iloilo 6th DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Barrido, Ajuy, Iloilo
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Iloilo 6th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱3.4M total · 0 flags

4. Implementation

Contract Amount

₱3,440,140.76

Progress

Past target date (DPWH On-Going)

Start Date

July 4, 2025

Target End

October 6, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.