Bridges18IF0044

RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, MATAG-OB BRIDGE (B00200LT) ALONG LIBUNGAO -MATAG-OB - PALOMPON ROAD

RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, MATAG-OB BRIDGE (B00200LT) ALONG LIBUNGAO -MATAG-OB - PALOMPON ROAD is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱5,585,223.41. Status: Reported complete (DPWH). Contractor on record: RJIR ENT CORP 34843. Figures trace to dpwh.

Leyte 4th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 34843

657 projects · ₱15.9B total · 0 flags

Other projects by this contractor

View all 657 projects →

4. Implementation

Contract Amount

₱5,585,223.41

Progress

Reported complete (DPWH)

Start Date

February 22, 2018

Target End

June 6, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.