REHABILITATION OF MULTI-PPURPOSE BUILDING (COVERED COURT), PHASE 3, MANUYO 3, LAS PINAS CITY

REHABILITATION OF MULTI-PPURPOSE BUILDING (COVERED COURT), PHASE 3, MANUYO 3, LAS PINAS CITY is a DPWH-tracked public work in Las Piñas-Muntinlupa DEO, National Capital Region. Reported contract value: ₱4,899,998.87. Status: Reported complete (DPWH). Contractor on record: V F LABAO CONST CORP. Figures trace to dpwh.

Las Piñas-Muntinlupa DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱32,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Slope Protection along Las Pinas River, Barangay Pulanglupa 2, Las Piñas City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Las Piñas-Muntinlupa DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,899,998.87

Progress

Reported complete (DPWH)

Start Date

July 12, 2018

Target End

January 7, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.