Water Provision and Storage19IA0115

CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS) FY 2019

CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS) FY 2019 is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱3,965,500.00. Status: Reported complete (DPWH). Contractor on record: M P BANTASAN CONST AND ALLIED SERVICES. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱3,965,500.00

Progress

Reported complete (DPWH)

Start Date

November 14, 2019

Target End

February 11, 2020

5. Audit