Roads21L00116

CONSTRUCTION OF BYPASS ROAD - MATIAO - MAGSAYSAY COASTAL ROAD PACKAGE 3, DAVAO ORIENTAL

CONSTRUCTION OF BYPASS ROAD - MATIAO - MAGSAYSAY COASTAL ROAD PACKAGE 3, DAVAO ORIENTAL is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱120,223,423.46. Status: Reported complete (DPWH). Contractor on record: MAER SUMMIT KONSTRUKT CO. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱120,223,423.46

Progress

Reported complete (DPWH)

Start Date

April 26, 2021

Target End

July 29, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.