Rehabilitation / Major Repair of Flood Control Structure23DH0100

Repair / Rehabilitation of River Control along Sta. Cruz River, Sta. Cruz Section Barangay Patimbao ( Sta. 000+100 - Sta. 000+139 ) (RS) and Barangay Pagsawitan ( Sta. 000+548 - Sta. 000+596) (LS) UPSTREAM, Sta. Cruz, Laguna

Repair / Rehabilitation of River Control along Sta. Cruz River, Sta. Cruz Section Barangay Patimbao ( Sta. 000+100 - Sta. 000+139 ) (RS) and Barangay Pagsawitan ( Sta. 000+548 - Sta. 000+596) (LS) UPSTREAM, Sta. Cruz, Laguna is a DPWH-tracked public work in SANTA CRUZ (CAPITAL) (LAGUNA), LAGUNA, Region IV-A. Reported contract value: ₱18,607,381.02. Status: Reported complete (DPWH). Contractor on record: TRIPLE EAGLE CONST AND TRADING. Figures trace to sumbong.

SANTA CRUZ (CAPITAL) (LAGUNA), LAGUNA, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Malaban, Bi±an City, Laguna
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Laguna 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱18,607,381.02

Progress

Reported complete (DPWH)

Start Date

November 23, 2023

Target End

June 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.