Bridges25JB0064

REPLACEMENT OF PERMANENT WEAK BRIDGES TUTUA BRIDGE (B00587MN) ALONG DIPOLOG-OROQUIETA NATIONAL ROAD (PHASE II)

REPLACEMENT OF PERMANENT WEAK BRIDGES TUTUA BRIDGE (B00587MN) ALONG DIPOLOG-OROQUIETA NATIONAL ROAD (PHASE II) is a DPWH-tracked public work in Zamboanga del Norte 1st DEO, Region IX. Reported contract value: ₱2,762,164.47. Status: Past target date (DPWH On-Going). Contractor on record: RUDHIL CONST. Figures trace to dpwh.

Zamboanga del Norte 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Dapitan River, Ilaya Bridge (Upstream), Ilaya, Dapitan City, Zamboanga Del Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Zamboanga del Norte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱2,762,164.47

Progress

Past target date (DPWH On-Going)

Start Date

March 26, 2025

Target End

April 25, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.