Flood Control and Drainage19EB0049

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONST. OF FLOOD MITIGATION STRUCTURE ALONG AMNAY RIVER (ILVITA SECT.), SABLAYAN, OCC. MINDORO

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONST. OF FLOOD MITIGATION STRUCTURE ALONG AMNAY RIVER (ILVITA SECT.), SABLAYAN, OCC. MINDORO is a DPWH-tracked public work in Mindoro Occidental DEO, Region IV-B. Reported contract value: ₱39,198,945.50. Status: Reported complete (DPWH). Contractor on record: HGG BUILDERS. Figures trace to dpwh.

Mindoro Occidental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-A-19-0000617

₱1,331,464,000.00 · FY2019

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

233 projects · ₱17.1B total · 0 flags

4. Implementation

Contract Amount

₱39,198,945.50

Progress

Reported complete (DPWH)

Start Date

June 25, 2019

Target End

April 1, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.