Buildings and Facilities19AH0155

CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL),BRGY. GUMOT, SAN FABIAN, PANGASINAN

CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL),BRGY. GUMOT, SAN FABIAN, PANGASINAN is a DPWH-tracked public work in Pangasinan 2nd DEO, Region I. Reported contract value: ₱1,950,300.00. Status: Reported complete (DPWH). Contractor on record: MIGHTYWAY CONST AND SUPPLY 40895. Figures trace to dpwh.

Pangasinan 2nd DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,950,300.00

Progress

Reported complete (DPWH)

Start Date

July 10, 2019

Target End

September 22, 2019

5. Audit