Water Provision and Storage23EG0050

CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY BINDUYAN, PUERTO PRINCESA CITY, PALAWAN

CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY BINDUYAN, PUERTO PRINCESA CITY, PALAWAN is a DPWH-tracked public work in Palawan 3rd DEO, Region IV-B. Reported contract value: ₱9,799,887.89. Status: Reported complete (DPWH). Contractor on record: YURICH BUILDERS AND CONST SUPPLY INC 37064. Figures trace to dpwh.

Palawan 3rd DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Maoyon, Puerto Princesa City, Palawan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Palawan 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 37064

153 projects · ₱5.1B total · 0 flags

Other projects by this contractor

No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ABORLAN RIVER WATERWAY, PTO. PRINCESA SOUTH ROAD, UPSTREAM LEFTSIDE, ABORLAN, PALAWAN

Region IV-B, Region IV-B

2025₱229.9M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ABORLAN RIVER WATERWAY, PTO. PRINCESA SOUTH ROAD, DOWNSTREAM RIGHTSIDE, ABORLAN, PALAWAN

Region IV-B, Region IV-B

2025₱229.9M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITUIES- CONST. OF PUNANG RIVER FLOOD CONTROL STRUCTURE, SOFRONIO, ESPANOLA, PALAWAN

Region IV-B, Region IV-B

2024₱193.0M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONSTRUCTION OF MARABAHAY SHORE PROTECTION STRUCTURE/CAUSEWAY, BATARAZA, PALAWAN

Region IV-B, Region IV-B

2023₱193.0M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF RIZAL AVENUE EXTENSION BOARDWALK, BRGY. BANCAO-BANCAO, PTO. PRINCESA CITY,

Region IV-B, Region IV-B

2023₱186.1M
Past target date (DPWH On-Going)
No sat.

WIDENING OF PERMANENT BRIDGES- BABUYAN BRIDGE (B00095PW) ALONG PUERTO PRINCESA NORTH ROAD, PALAWAN

Region IV-B, Region IV-B

2023₱159.2M
Reported complete (DPWH)
View all 153 projects →

4. Implementation

Contract Amount

₱9,799,887.89

Progress

Reported complete (DPWH)

Start Date

March 28, 2023

Target End

January 25, 2024

5. Audit