Flood Control and Drainage17EB0130

CLUSTER FCD04: CONSTRUCITON/REHABILITATION OF VARIOUS FLOOD MITIGATION FACILITIES ALONG MAJOR RIVER BASINS: A) BUSUANGA RIVER FLOOD CONTROL STRUCTURE, STA.0+000-STA.0+390, SAN JOSE, B) BUSUANGA RIVER FLOOD CONTROL STRUCTURE, STA. 0+000-STA.0+390, SAN JO

CLUSTER FCD04: CONSTRUCITON/REHABILITATION OF VARIOUS FLOOD MITIGATION FACILITIES ALONG MAJOR RIVER BASINS: A) BUSUANGA RIVER FLOOD CONTROL STRUCTURE, STA.0+000-STA.0+390, SAN JOSE, B) BUSUANGA RIVER FLOOD CONTROL STRUCTURE, STA. 0+000-STA.0+390, SAN JO is a DPWH-tracked public work in Mindoro Occidental DEO, Region IV-B. Reported contract value: ₱16,814,136.83. Status: Reported complete (DPWH). Contractor on record: ED1SON DEVELOPMENT. Figures trace to dpwh.

Mindoro Occidental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Lumintao Flood Control (Tanyag Section), Calintaan, Mindoro Occidental Lone District
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0032447

₱50,584.00 · FY2016

Released to Clarencio Calagos Memorial School of Fisheries Ter (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

351 projects · ₱8.3B total · 0 flags

4. Implementation

Contract Amount

₱16,814,136.83

Progress

Reported complete (DPWH)

Start Date

November 7, 2017

Target End

April 13, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.