Buildings and Facilities23CC0577

CONSTRUCTION OF MULTI-PURPOSE FACILITY (PLARIDEL PUBLIC MARKET), BARANGAY BANGA 1ST, PLARIDEL, BULACAN

CONSTRUCTION OF MULTI-PURPOSE FACILITY (PLARIDEL PUBLIC MARKET), BARANGAY BANGA 1ST, PLARIDEL, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱95,033,835.29. Status: Past target date (DPWH On-Going). Contractor on record: EIRISH BUILDERS. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱23,250,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Angat River at Banga 2nd Section, Plaridel, Bulacan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bulacan 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

126 projects · ₱3.4B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONST. OF ROAD,PHASE II,SITIO TALAMSI I-SITIO KAMB

Bulacan 3rd DEO, Region III

2025₱142.5M
Past target date (DPWH On-Going)
No sat.

CONVERGE. AND SPECIAL SUPPORT PROG. - SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRAT. PUBLIC BLDGSS/ FACILITIES - CONST.OF ROAD, PHASE I, SITIO TALAMSI I - SITIO KAM

Bulacan 3rd DEO, Region III

2025₱142.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW MUNICIPAL HALL), ANGAT, BULACAN

Bulacan 2nd DEO, Region III

2023₱117.5M
Reported complete (DPWH)
No sat.

STATE UNIVERSITIES AND COLLEGES (SUCS)-ESTABLISHMENT AND/OR SUPPORT TO THE COLLEGE OF MEDICINES, SAN RAFAEL CAMPUS-BULACAN STATE UNIVERSITY, SAN RAFAEL, BULACAN, PROVINCE OF BULACAN

Region III, Region III

2024₱98.5M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER, LONGOS - ZAMORA SECTION, STA. 06+220 - STA. 06+340, MEYCAUAYAN, BULACAN

Bulacan 2nd DEO, Region III

2025₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, CITY COLLEGE OF SAN JOSE DEL MONTE SCHOOL OF NURSING AND ALLIED HEALTH (PHASE 2), BARANGAY MINUYAN PROPER, CITY OF SAN JOSE DEL MONTE, BULACAN

Bulacan 2nd DEO, Region III

2025₱96.0M
Past target date (DPWH On-Going)
View all 126 projects →

4. Implementation

Contract Amount

₱95,033,835.29

Progress

Past target date (DPWH On-Going)

Start Date

December 21, 2023

Target End

October 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.