Flood Control and Drainage16AC0021

CONST. OF RIVER FLOOD CONTROL, GABION REVETMENT WALL / STONE MASONRY, NAMBARAN, STO. DOMINGO, I. SUR

CONST. OF RIVER FLOOD CONTROL, GABION REVETMENT WALL / STONE MASONRY, NAMBARAN, STO. DOMINGO, I. SUR is a DPWH-tracked public work in Ilocos Sur 1st DEO, Region I. Reported contract value: ₱1,880,396.38. Status: Reported complete (DPWH). Contractor on record: FIT CONST 35857. Figures trace to dpwh.

Ilocos Sur 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,880,396.38

Progress

Reported complete (DPWH)

Start Date

February 11, 2016

Target End

March 31, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.