Construction of Flood Mitigation Structure24A00493

Construction of Flood Control Riverbank Structure along Agno and Allied Rivers, Alcala, Pangasinan

Construction of Flood Control Riverbank Structure along Agno and Allied Rivers, Alcala, Pangasinan is a DPWH-tracked public work in ALCALA (PANGASINAN), PANGASINAN, Region I. Reported contract value: ₱96,499,995.51. Status: Reported complete (DPWH). Contractor on record: SILVERWOLVES CONST CORP. Figures trace to sumbong.

ALCALA (PANGASINAN), PANGASINAN, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tagamusing and Allied River, Binalonan, Pangasinan ( Package 1 )
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0007434

₱1,946,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0003000

₱441,770.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0007435

₱180,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROI-24-0001275

₱159,815.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

179 projects · ₱19.9B total · 9 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF REVETMENT AND OTHER IMPROVEMENTS ALONG BALUCTOT RIVER, EAST SIDE, BRGY. SALAWAG, DASMARIÑAS, CAVITE

Region IV-A, Region IV-A

2024₱241.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF REVETMENT AND OTHER IMPROVEMENTS ALONG BALUCTOT RIVER, EAST SIDE, BRGY. PALIPARAN III, DASMARIÑAS, CAVITE (PHASE I)

Region IV-A, Region IV-A

2024₱241.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BENGUET NUEVA VIZCAYA RD, K0283+368 - K0283+475

Cordillera Administrative Region, Cordillera Administrative Region

2023₱241.3M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BENGUET NUEVA VIZCAYA RD, K0283+475 - K0283+575

Cordillera Administrative Region, Cordillera Administrative Region

2023₱241.3M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROAD SAFETY DEVICES ALONG BAUANG-BAGUIO CITY ROAD, K0261+100 - K0261+300, K0262+300 - K0262+400, K0262+900 - K0263+100, K0263+500 - K0263+900, K0269+600 - K0269+750,

Region I, Region I

2023₱241.2M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG PAGBAHAN RIVER, PHASE 1, BRGY. SAN VICENTE, SANTA CRUZ, OC

Region IV-B, Region IV-B

2024₱241.2M
Reported complete (DPWH)
View all 179 projects →

4. Implementation

Contract Amount

₱96,499,995.51

Progress

Reported complete (DPWH)

Start Date

May 3, 2024

Target End

December 4, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.