Flood Control and Drainage18OE0063

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF LOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS BANK IMPROVEMENT (STEEL SHEET PILE) ESTERO DE SUNOG APOG STA. 0+081.20 TO STA)

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF LOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS BANK IMPROVEMENT (STEEL SHEET PILE) ESTERO DE SUNOG APOG STA. 0+081.20 TO STA) is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱48,793,511.98. Status: Reported complete (DPWH). Contractor on record: ALPHA. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Bank Improvement (Steel Sheet Pile) Estero de Sunog Apog, Sta. 0+260.80 to Sta. 0+400.40, Brgy. 132 and Brgy. 137, Manila City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-18-0033895

₱0.00 · FY2018

Released to Dacap Norte National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

831 projects · ₱32.1B total · 0 flags

4. Implementation

Contract Amount

₱48,793,511.98

Progress

Reported complete (DPWH)

Start Date

February 26, 2018

Target End

August 24, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.