Buildings and Facilities21CD0057

CONSTRUCTION OF MULTI-PURPOSE BUILDING, STA. LUCIA ES, STA. LUCIA, ANGAT, BULACAN

CONSTRUCTION OF MULTI-PURPOSE BUILDING, STA. LUCIA ES, STA. LUCIA, ANGAT, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱1,918,014.26. Status: Reported complete (DPWH). Contractor on record: YPR GEN CONTRACTOR AND CONST SUPPLY INC 45002. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Bulo River (Sta. Lucia Section), Barangay Sta. Lucia, San Miguel, Bulacan
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Bulacan 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 45002

196 projects · ₱6.8B total · 0 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD MITIGATING STRUCTURE, TINGARAY RIVER, UPSTREAM R/S, BRGY. POBLACION, FERROL, ROMBLON

Region IV-B, Region IV-B

2025₱247.5M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD MITIGATING STRTUCTURE, TINGARAY

Region IV-B, Region IV-B

2025₱247.5M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF CAUSEWAY ALONG BRGY. AMBULONG SECTION, MAGDIWANG, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2024₱236.4M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. ADELA, SAN JOSE, OCC. MINDORO

Region IV-B, Region IV-B

2024₱232.4M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF RIVERSIDE PROTECTION STRUCTURE, PILI RIVER, UPSTREAM, POBLACION, SAN FERNANDO, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2025₱230.1M
Past target date (DPWH On-Going)
No sat.

FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF RIVERSIDE PROTECTION STRUCTURE, DOWNSTREAM, BRGY. PUNONG, SAN FERNANDO, ROMBLON

Region IV-B, Region IV-B

2025₱229.8M
Past target date (DPWH On-Going)
View all 196 projects →

4. Implementation

Contract Amount

₱1,918,014.26

Progress

Reported complete (DPWH)

Start Date

March 8, 2021

Target End

June 5, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.