Buildings and Facilities17JD0066

CONSTRUCTION OF 1 UNIT 1 STOREY 2 CL SCHOOL BUILDING SAN ANTONIO ES, POLANCO, ZAMBOANGA DEL NORTE

CONSTRUCTION OF 1 UNIT 1 STOREY 2 CL SCHOOL BUILDING SAN ANTONIO ES, POLANCO, ZAMBOANGA DEL NORTE is a DPWH-tracked public work in Zamboanga del Norte 1st DEO, Region IX. Reported contract value: ₱2,759,181.00. Status: Reported complete (DPWH). Contractor on record: MONTPHIL CONST CORP. Figures trace to dpwh.

Zamboanga del Norte 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,759,181.00

Progress

Reported complete (DPWH)

Start Date

November 6, 2017

Target End

February 28, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.