Buildings and Facilities18EE0194

CONSTRUCTION OF TWO STOREY 4 CL (2 REGULAR WORKSHOPS) MAGARA SCHOOL FORPHILIPPINE CRAFTSMEN ROXAS, PALAWAN

CONSTRUCTION OF TWO STOREY 4 CL (2 REGULAR WORKSHOPS) MAGARA SCHOOL FORPHILIPPINE CRAFTSMEN ROXAS, PALAWAN is a DPWH-tracked public work in Palawan 1st DEO, Region IV-B. Reported contract value: ₱8,997,483.42. Status: Reported complete (DPWH). Contractor on record: ALPHA. Figures trace to dpwh.

Palawan 1st DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Batacalan Bridge, CBNR, Palawan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-18-0005523

₱0.00 · FY2018

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱8,997,483.42

Progress

Reported complete (DPWH)

Start Date

August 23, 2018

Target End

February 18, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.