Bridges18DL0008

I. OPERATIONS A. ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM 3. BRIDGE PROGRAM A. RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES 8. KAGUISI BR. 2 (B00038AB) ALONG QUEZON-ALABAT-PEREZ RD

I. OPERATIONS A. ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM 3. BRIDGE PROGRAM A. RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES 8. KAGUISI BR. 2 (B00038AB) ALONG QUEZON-ALABAT-PEREZ RD is a DPWH-tracked public work in Quezon 4th DEO, Region IV-A. Reported contract value: ₱5,715,527.74. Status: Reported complete (DPWH). Contractor on record: JEMAK CONST. Figures trace to dpwh.

Quezon 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage Structure along Pandanan River, Brgy. Pandanan, Calauag, Quezon
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0032863

₱0.00 · FY2018

Released to San Roque National High Ro School (Kapitangan National High School Annex-San Roque) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱5,715,527.74

Progress

Reported complete (DPWH)

Start Date

February 15, 2018

Target End

April 15, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.