Roads17FI0013

ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATION

ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATION is a DPWH-tracked public work in Masbate 2nd DEO, Region V. Reported contract value: ₱35,660,766.87. Status: Reported complete (DPWH). Contractor on record: SPRING STAR CONST AND SUPPLY. Figures trace to dpwh.

Masbate 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱7,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures (Dike) along Panisihan River, Batuan, Masbate
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-17-0015128

₱1,390,000.00 · FY2017

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

225 projects · ₱6.8B total · 2 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - BALUD NATIONAL ROAD CONNECTING BARANG

Masbate 2nd DEO, Region V

2023₱135.1M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - C0NSTRUCTION/IMPROVEMENT OF ACCESS OF ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP) - BALUD - PALANI - PANUBIGAN - PAJO -TALISAY ROAD LEADING TO PALANI BEACHES, PANUBIGA

Masbate 2nd DEO, Region V

2023₱115.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - MANDAON - DAYHAGAN ROAD, PACKAGE 1, MASBATE

Masbate 2nd DEO, Region V

2024₱96.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS, MALUBI - CABANGCALAN - DAYHAGAN - TINIGBAN - MATABA ROAD, MASBATE, STA.5+101 - STA.6+245, AROROY, MASBATE

Masbate 2nd DEO, Region V

2022₱96.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS - MANDAON - DAYHAGAN - ROAD, STA.4+350 - STA.5+750, MANDAON, MASBATE

Masbate 2nd DEO, Region V

2022₱96.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - MALUBI - CABANGCALAN - DAYHAGAN - TINIGBAN - MATABA ROAD, MASBATE, STA. 3+892 - STA. 5+052, NET LENGTH = 2.320 LANE KM (1.160 KM), AROROY, MASBATE

Masbate 2nd DEO, Region V

2021₱96.5M
Reported complete (DPWH)
View all 225 projects →

4. Implementation

Contract Amount

₱35,660,766.87

Progress

Reported complete (DPWH)

Start Date

May 5, 2017

Target End

November 21, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.