Buildings and Facilities23D00058

CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARRACKS WITH PARKING), CAMP NAKAR, LUCENA CITTY, QUEZON, PHASE II

CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARRACKS WITH PARKING), CAMP NAKAR, LUCENA CITTY, QUEZON, PHASE II is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱4,824,992.00. Status: Reported complete (DPWH). Contractor on record: ARDA CONST AND SUPPLY. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

23 projects · ₱322.8M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF FIVE (5) STOREY AFP QUARTERS, BUILDING 1, LUCENA CITY, QUEZON, PHASE III

Region IV-A, Region IV-A

2024₱28.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 3. CONSTRUCTION OF ROAD, LALAGUNA - MONTECLARO - PISIPIS, LOPEZ

Quezon 4th DEO, Region IV-A

2024₱24.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 1. CONSTRUCTION OF LALAGUNA-CAWAYAN BARANGAY ROAD, LOPEZ, QUEZO

Quezon 4th DEO, Region IV-A

2024₱24.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 4. CONSTRUCTION OF STO. NIÑO IBABA - SUMALANG BARANGAY ROAD, LO

Quezon 4th DEO, Region IV-A

2024₱24.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM, ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 12. CONSTRUCTION OF CONCEPCION-KINALIN BARANGAY ROAD, LOPEZ, QUEZON

Quezon 4th DEO, Region IV-A

2023₱24.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM, ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 11. CONSTRUCTION OF LALAGUNA - MONTECLARO - PISIPIS ROAD, LOPEZ, QUEZON

Quezon 4th DEO, Region IV-A

2023₱19.8M
Reported complete (DPWH)
View all 23 projects →

4. Implementation

Contract Amount

₱4,824,992.00

Progress

Reported complete (DPWH)

Start Date

March 3, 2023

Target End

February 10, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.