Buildings and Facilities17BG0004

CONSTRUCTION OF MULTI PURPOSE BUILDING COVERED COURT, MACANIAO, ANGADANAN, ISABELA

CONSTRUCTION OF MULTI PURPOSE BUILDING COVERED COURT, MACANIAO, ANGADANAN, ISABELA is a DPWH-tracked public work in Isabela 3rd DEO, Region II. Reported contract value: ₱1,919,413.39. Status: Reported complete (DPWH). Contractor on record: E S PUA CONST 32631. Figures trace to dpwh.

Isabela 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,919,413.39

Progress

Reported complete (DPWH)

Start Date

February 13, 2017

Target End

July 12, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.