Buildings and Facilities20BH0044

CONSTRUCTION OF MULTI-PURPOSE BUILDING - BRGY. VILLA VICTORIA

CONSTRUCTION OF MULTI-PURPOSE BUILDING - BRGY. VILLA VICTORIA is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱2,970,000.00. Status: Reported complete (DPWH). Contractor on record: CAMBERWELL CONST AND SUPPLIES. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱41,652,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Rang-ay Flood Control, Section 1, Isabela
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Isabela 4th DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

237 projects · ₱3.3B total · 5 flags

Other projects by this contractor

Construction of Bongabong River Control, Brgy. Morente Section, Bongabong, Oriental Mindoro

BONGABONG (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱96.5M
Reported complete (DPWH)

Construction of Cagayan River Flood Control Project, Barangay Furao, Gamu, Isabela

GAMU (ISABELA), ISABELA, Region II

2024₱96.5M
Reported complete (DPWH)
No sat.

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONSTRUCTION OF PINACANAUAN RIVER FLOOD CONTROL STRUCTURE, BRGY. DICAMAY,

Isabela 3rd DEO, Region II

2025₱96.4M
Reported complete (100% progress, DPWH status On-Going)

Construction of Cagayan River Flood Control Project, Barangay Magsaysay, Naguilian, Isabela, Phase II

SAN MARIANO (ISABELA), ISABELA, Region II

2024₱96.4M
Reported complete (DPWH)

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL PROJECT BARANGAY PALATTAO (CONTINUATION), NAGUILIAN

Isabela 3rd DEO, Region II

2025₱96.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCES ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) - ACCESS ROAD LEADING TO PALANAN AIRPORT, PALANAN, ISABELA

Isabela 3rd DEO, Region II

2021₱96.3M
Reported complete (DPWH)
View all 237 projects →

4. Implementation

Contract Amount

₱2,970,000.00

Progress

Reported complete (DPWH)

Start Date

September 9, 2020

Target End

March 21, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.