Flood Control and Drainage18DN0146

ORGANIZATIONAL OUTCOME 2: REHABILITATION WITH SLOPE PROTECTION OF TAYTAY RIVER, PHASE 2, BRGY SAN JUAN, TAYTAY, RIZAL

ORGANIZATIONAL OUTCOME 2: REHABILITATION WITH SLOPE PROTECTION OF TAYTAY RIVER, PHASE 2, BRGY SAN JUAN, TAYTAY, RIZAL is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱14,700,000.00. Status: Reported complete (DPWH). Contractor on record: HONY TRADING. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱14,700,000.00

Progress

Reported complete (DPWH)

Start Date

July 23, 2018

Target End

March 19, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.