Roads18GK0130

CONSTRUCTION OF ESCALANTE CITY CIRCUMFERENTIAL ROAD, ESCALANTE CITY, NEGROS OCCIDENTAL, (STA. 01+288.81 - STA. 02+288.81)

CONSTRUCTION OF ESCALANTE CITY CIRCUMFERENTIAL ROAD, ESCALANTE CITY, NEGROS OCCIDENTAL, (STA. 01+288.81 - STA. 02+288.81) is a DPWH-tracked public work in Negros Occidental 1st DEO, Negros Island Region. Reported contract value: ₱28,179,011.70. Status: Reported complete (DPWH). Contractor on record: TRIMLUV BUILDERS AND SUPPLY 33467. Figures trace to dpwh.

Negros Occidental 1st DEO, Negros Island Region
Region: Negros Island Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱28,179,011.70

Progress

Reported complete (DPWH)

Start Date

May 24, 2018

Target End

January 24, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.