Buildings and Facilities18ED0113

CONSTRUCTION OF 2 UNITS 2 STOREY ICT LAB, 2 STOREY SCI LAB AT INARAWAN NHS, NAUJAN, ORIENTAL MINDORO

CONSTRUCTION OF 2 UNITS 2 STOREY ICT LAB, 2 STOREY SCI LAB AT INARAWAN NHS, NAUJAN, ORIENTAL MINDORO is a DPWH-tracked public work in Mindoro Oriental DEO, Region IV-B. Reported contract value: ₱17,604,126.50. Status: Reported complete (DPWH). Contractor on record: FRAMECON BUILDERS. Figures trace to dpwh.

Mindoro Oriental DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱17,604,126.50

Progress

Reported complete (DPWH)

Start Date

June 26, 2018

Target End

March 16, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.