Flood Control and Drainage24JA0070

BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SANGA PRESSA CREEK, KM. 4, BRGY. STA. MARIA, ZAMBOANGA CITY

BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SANGA PRESSA CREEK, KM. 4, BRGY. STA. MARIA, ZAMBOANGA CITY is a DPWH-tracked public work in Zamboanga City 2nd DEO, Region IX. Reported contract value: ₱14,646,889.89. Status: Past target date (DPWH On-Going). Contractor on record: EL DOLLIARES CONST INC. Figures trace to dpwh.

Zamboanga City 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Sanga Pressa Creek, Km. 4, Brgy. Sta. Maria, Zamboanga City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Zamboanga City 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,646,889.89

Progress

Past target date (DPWH On-Going)

Start Date

May 15, 2024

Target End

September 29, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.