CONSTRUCTION OF SEAWALL, BRGY. POBLACION, BANATE, ILOILO, STA. 000 + (-063.1) - STA. 000 + 293.1

CONSTRUCTION OF SEAWALL, BRGY. POBLACION, BANATE, ILOILO, STA. 000 + (-063.1) - STA. 000 + 293.1 is a DPWH-tracked public work in Iloilo 2nd DEO, Region VI. Reported contract value: ₱5,171,819.30. Status: Reported complete (DPWH). Contractor on record: G UY CONST 27999. Figures trace to dpwh.

Iloilo 2nd DEO, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱5,171,819.30

Progress

Reported complete (DPWH)

Start Date

July 11, 2019

Target End

September 6, 2019

5. Audit