Buildings and Facilities20K00386

CONSTRUCTION OF 1ST2CL, 77TH PC ES, TARAKA, LANAO DEL SUR

CONSTRUCTION OF 1ST2CL, 77TH PC ES, TARAKA, LANAO DEL SUR is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱4,364,877.06. Status: Reported complete (DPWH). Contractor on record: MAGS TRADING AND CONST 38717. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,364,877.06

Progress

Reported complete (DPWH)

Start Date

January 15, 2021

Target End

April 9, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.