Roads23B00041

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): SIPAG- ACCESS ROADS AND /OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION OF TUGUEGARAO CIRCUMFERENTIAL DIKE ROAD

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): SIPAG- ACCESS ROADS AND /OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION OF TUGUEGARAO CIRCUMFERENTIAL DIKE ROAD is a DPWH-tracked public work in Region II, Region II. Reported contract value: ₱187,936,374.99. Status: Reported complete (DPWH). Contractor on record: EGB CONST CORP FORMERLY: EGB CONST. Figures trace to dpwh.

Region II, Region II
Region: Region II

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

646 projects · ₱29.0B total · 49 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGE - MINANGA BR. (B01129LZ) ALONG MAHARLIKA HIGHWAY

Region II, Region II

2025₱241.2M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0399 + 008 - K0400 + 009, K0405 + 885 - K0406 + 340, K0439 + 000 - K0439 + 557, K0444 + 230 - K0447+ 200, K0447 + 7

Region II, Region II

2024₱213.3M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONSTRUCTION OF MANSALAY COASTAL ROAD, DEL MUNDO SECTION, MANSALAY, ORIENTAL MINDORO

Region IV-B, Region IV-B

2023₱212.3M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- SECONDARY ROADS- MINDORO WEST COASTAL ROAD, K0417+000 - K0445+498 (INTERMITTENT SECTIONS), ABRA DE ILOG, OCC. MINDORO

Region IV-B, Region IV-B

2025₱202.1M
Past target date (DPWH On-Going)
No sat.

CSSP-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION (COMPLETION) OF TUROD-BANQUERO BRIDGE, REINA MERCEDES, ISABELA

Isabela 3rd DEO, Region II

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)-CONSTRUCTION OF DIVERSION/BY-PASS ROAD OF CORY AQUINO BOUL

Region V, Region V

2025₱192.0M
Past target date (DPWH On-Going)
View all 646 projects →

4. Implementation

Contract Amount

₱187,936,374.99

Progress

Reported complete (DPWH)

Start Date

May 25, 2023

Target End

December 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.