Construction of Slope Protection Structure23NA0050

Construction of Slope Protection along Mahaba Bridge Approaches, Cabadbaran City, Agusan de Norte

Construction of Slope Protection along Mahaba Bridge Approaches, Cabadbaran City, Agusan de Norte is a DPWH-tracked public work in TUBAY (AGUSAN DEL NORTE), AGUSAN DEL NORTE, Region XIII. Reported contract value: ₱48,999,995.59. Status: Reported complete (DPWH). Contractor on record: ARQ BUILDERS. Figures trace to sumbong.

TUBAY (AGUSAN DEL NORTE), AGUSAN DEL NORTE, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Agay River, Brgy. Balang-Balang RTR, Agusan del Norte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Agusan del Norte District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,999,995.59

Progress

Reported complete (DPWH)

Start Date

September 13, 2023

Target End

May 9, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.