Buildings and Facilities21JC0081

CONSTRUCTION/COMPLETION (2STY4CL WORKSHOP COMBINED W/ TOILET) AT KIPIT AGRO-FISHERY NHS, LABASON, ZAMBOANGA DEL NORTE

CONSTRUCTION/COMPLETION (2STY4CL WORKSHOP COMBINED W/ TOILET) AT KIPIT AGRO-FISHERY NHS, LABASON, ZAMBOANGA DEL NORTE is a DPWH-tracked public work in Zamboanga del Norte 3rd DEO, Region IX. Reported contract value: ₱1,359,120.04. Status: Reported complete (DPWH). Contractor on record: JZL BUILDERS. Figures trace to dpwh.

Zamboanga del Norte 3rd DEO, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱4,200,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Barangay Kauswagan, Sergio Osmena, Zamboanga del Norte
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Zamboanga del Norte 3rd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,359,120.04

Progress

Reported complete (DPWH)

Start Date

October 11, 2021

Target End

November 9, 2021

5. Audit