Buildings and Facilities22HL0069

BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION , STA. CATALINA, NEGROS ORIENTAL

BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION , STA. CATALINA, NEGROS ORIENTAL is a DPWH-tracked public work in Negros Oriental 3rd DEO, Negros Island Region. Reported contract value: ₱9,900,000.00. Status: Reported complete (DPWH). Contractor on record: MG CONST. Figures trace to dpwh.

Negros Oriental 3rd DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱36,981,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along La Libertad River, Sta. 0+000 - Sta. 2+250, La Libertad, Negros Oriental
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Negros Oriental 3rd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

213 projects · ₱1.4B total · 1 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 002: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM: CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JAGONIPA RIVER (UPST

Negros Oriental 3rd DEO, Negros Island Region

2025₱72.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES / FACILITIES: CONSTRUCTION OF FLOOD CONTROL STRUCTURE (UPSTREAM), MAYABON, ZAMBOANGUITA

Negros Oriental 3rd DEO, Negros Island Region

2025₱48.9M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM: CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS : PRIMARY ROADS: DUMAGUETE SOUTH RD : K0033 + 518 - K0034 + 324, (K0033 + 0

Negros Oriental 3rd DEO, Negros Island Region

2024₱32.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES: CONSTRUCTION OF ROAD, TIMBAO - LIPTONG,

Negros Oriental 3rd DEO, Negros Island Region

2025₱29.3M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF WHITE COPRA (WHOLE NUT BUILDING), ZAMBOANGUITA, NEGROS ORIENTAL

Region VII, Region VII

2024₱26.3M
Reported complete (DPWH)
No sat.

DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP) - ACCESS ROAD LEADING TO BRAVO GOLF COURSE, RESORT & SPA SIBULAN, PULANGBATO FALLS & TIERRA ALTA RESIDENTIAL RESORT, VALENCIA-BRGY. SAN SANTONIO, SIBULAN, NEGROS ORIENTAL

Negros Oriental 2nd DEO, Negros Island Region

2023₱24.5M
Reported complete (DPWH)
View all 213 projects →

4. Implementation

Contract Amount

₱9,900,000.00

Progress

Reported complete (DPWH)

Start Date

March 23, 2022

Target End

February 11, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.